Teralba Pty Ltd

Construction of Engineered Footing for Mixer Tank inside an existing Factory

Works included:

  • Cut existing slab, remove and then dig footing to 1200mm deep
  • Removal of all waste off site
  • Drill 600mm piers up to 3500mm deep
  • Form and pour sides and base of footing working with engineered drawings
  • Integrate load plates and form & pour top slab ready for Tank installation